Site planning

Virtual Storage Platform E1090 Hardware Reference Guide

Version
93-07-2x
93-07-0x
Audience
anonymous
Part Number
MK-97HM85054-03

All planning activities should be scheduled and completed before the equipment is delivered.

The planning process includes:

  • Planning hardware configuration, such as system component layout in the rack and drive allocation.
  • Planning for specific network topologies, cabling configurations, network switches, and cabling of connected host computers.
  • Ensuring all cables for specific controller and drive tray configurations are properly ordered.
  • Verifying all electrical service wiring is installed at the predetermined location.
Complete the suggested tasks before receiving and installing the storage system:
  • Prepare a preliminary layout of the installation.
  • Review the power and the heating, ventilation, and air-conditioning requirements before ordering any additional support equipment.
  • Make a final layout of the installation and review the layout with the Hitachi Vantara representative.
  • Verify the installation of electrical service wiring at the predetermined location is proper before installing the storage system.
  • Verify all additional equipment, such as switches and host computers, is installed and operational.