Editing a migration project

Nondisruptive Migration User Guide

Version
9.6.0
Audience
anonymous
Part Number
MK-92RD8086-11

After a migration project is created, and before performing data migration, you can edit migration project information.

You can edit the following migration project information:
  • Settings for resource groups that are created in the virtual storage machine of the target storage system
  • Settings that define the mapping between source and target storage ports
  • Settings that define the external paths between the ports of the source storage system and the external or bidirectional ports of the target storage system
  1. On the Mobility tab, select Migration Projects.
  2. Expand the tree and select a target storage system.
  3. In the Migration Projects list, select a migration project.
  4. From the Migration Project Actions menu, choose one of the following options:

    Option

    Description

    Edit Resource Group Mapping

    Select the resource groups on the target storage system to map to the resource groups on the source storage system, and then click OK. You can verify the new resource group mapping by opening the Edit Resource Group Mapping dialog box again.

    Tip: If you change the mapping to the resource groups on the target storage system, the information about the user groups and roles that are assigned to the resource groups on the source storage system are not inherited. Edit the resource group mapping, and then assign resource groups and roles to the user groups on the target storage system.

    Edit Port Mapping

    Select the ports of the target storage system to map to the ports of the source storage system, or change the destination of ports that are already mapped, and then click OK. You can verify the new I/O path mapping by opening the Edit Port Mapping dialog box again.

    Edit External Path Setting

    Specify paths in accordance with the displayed instructions, and then click Submit. The submitted plan is registered as a task. Check the task results in the Tasks & Alerts tab. You can verify the new external path mapping by opening the Edit External Path Setting dialog box again.

Resource group mapping, port mapping, and external path settings are updated for the migration project.