Responding to tasks

Ops Center Automator User Guide

Version
11.0.x
Audience
anonymous
Part Number
MK-99AUT001-22

Some tasks might require input from a user to continue running (for example, a manager's approval) and might send an email notification indicating that a response is required. A task that is pending a response is in the Waiting for Input status.

  1. On the Tasks tab, select the task that needs a response, then click Input Response.
  2. In the Input Response dialog box, input the response.
  3. Click OK.