Operation can be continued by using the volume at the intermediate site if the primary site fails in a PPRC cascade configuration. Switch operations from the primary site to the intermediate site first if the primary site fails. The following procedure assumes that site B is the primary site, site A is the intermediate site, and site C is the secondary site in a PPRC cascade configuration. The procedure describes how to resume business at site A and then restore the duplex configuration.
After you have completed this procedure, site A becomes the primary site in the PPRC multi-target configuration.
To change the PPRC multi-target configuration back to the original PPRC cascade configuration, see Configuring PPRC cascade.