If you have registered a split time for the SIz CTG, you must delete the split time before you can add, resume, or suspend pairs from BCM. To prevent the TCz command to resume split pairs from being rejected, pair the SIz volumes (DUPLEX status) before resuming the pairs that you have split (Split/SUSPOP status).
Complete the following steps to register a new split time for the SIz CTG:
- Delete the current registered split time.
- Register the new split time.
For more information about registering split times, see the
Hitachi Business Continuity Manager User Guide.