All cables should have been labeled as a pre-requisite step.
- Connect the network management drop to eth1.
- Reconnect the Cluster Interconnect Cables, C1 -> C1 & C3 -> C3.
- Plugin all customer facing EVS 10GiB Ethernet Cables exactly as how they came off the old node.
- Reconnect the Fiber Channel Cables, left to right - 4,3,2,1.
- Verify that all Management, Cluster Interconnect, Network, and Storage Cables to the Replacement node are in place.