Plugging in all remaining cable to the new node

Virtual Storage Platform One File 32 Gen2 Hardware Reference

Version
15.6.x
Audience
anonymous
Part Number
MK-24VSP1F009-00
ft:lastEdition
2026-08-28

All cables should have been labeled as a pre-requisite step.

  1. Connect the network management drop to eth1.
  2. Reconnect the Cluster Interconnect Cables, C1 -> C1 & C3 -> C3.
  3. Plugin all customer facing EVS 10GiB Ethernet Cables exactly as how they came off the old node.
  4. Reconnect the Fiber Channel Cables, left to right - 4,3,2,1.
  5. Verify that all Management, Cluster Interconnect, Network, and Storage Cables to the Replacement node are in place.