Recovering from a target UR secondary site failure that occurs before deleting a source UR pair "after migration is complete"

Global Active Device for VSP One Block

Version
10.5.x
File Size
25537 KB
Audience
anonymous
Part Number
MK-23VSP1B011-11
ft:lastEdition
2026-06-23

The table below shows the changes in the pair status before and after a failure.

Pair type Pair status before failure Pair status after failure
P-VOL S-VOL P-VOL S-VOL
GAD pair PAIR

(Mirror (RL))

PAIR

(Mirror (RL))

PAIR

(Mirror (RL))

PAIR

(Mirror (RL))

Source UR pair PAIR PAIR PAIR PAIR
Target UR pair PAIR PAIR PAIR1 or PSUE1, 2 -

(PSUE2)

Note:
  1. The pair status depends on the settings of the system option modes (SOMs) 448 and 449.
  2. The status after powering on the source primary site.

When recovering from this failure, you must perform this failure recovery operations in the target UR environment, and then remove the source UR environment because the system environmental migration for the remote copy function is complete.



  1. Remove the failure on the storage system at the target UR secondary site.
  2. Resynchronize the target UR pair.
The subsequent section provides how to remove the source UR environment in accordance with the procedure in Removing the source environment.