For a detailed description of the steps used to create a GAD pair, see Workflow for creating a GAD environment.



  1. Configure the target GAD secondary site by using the storage system at the secondary site of the temporary GAD pair used for migration as the storage system at the target GAD primary site.
  2. Stop the CCI instance on the server that is connecting to the storage system at the primary site.
  3. Add the information of the target GAD pair to the configuration definition file for the CCI instance you stopped.
  4. Start the CCI instance.
  5. Create a GAD pair by specifying the volume used as the S-VOL of the temporary GAD pair used for migration as the P-VOL of the target GAD pair.

    The pair status of this target GAD pair does not change to PAIR and remains COPY.