- Recover from the failure in the remote path.
-
Resynchronize the target GAD pair by specifying the P-VOL.
Command example:
pairresync –g oraHA02 –IH2
-
Verify that the pair status of the target GAD pair has
changed to COPY.
Command example:
pairdisplay –g oraHA02 –fcxe –IH2 Group PairVol(L/R) (Port#,TID, LU),Seq#, LDEV#.P/S, Status,Fence,%, P-LDEV# M CTG JID AP EM E-Seq# E-LDEV# R/W QM DM P PR oraHA02 dev02(L) (CL1-C-0, 0, 0)833333 1111.P-VOL COPY NEVER , 55 2222 - - 2 1 - - - L/M - D N D oraHA02 dev02(R) (CL1-C-0, 0, 0)844444 2222.S-VOL COPY NEVER ,----- 1111 - - 2 1 - - - B/B - D N D
- Continue data migration from the procedure that you performed before the failure.