Hitachi Virtual Storage Platform One Block 20 series (VSP One Block 20 series) storage systems are designed for self-installation, so you can install and set up your storage system for the first time without assistance from a Hitachi Vantara representative.

Site preparation
Before you install the storage system, make sure your data center meets all site preparation requirements as specified in the Hardware Guide for VSP One Block 20 Series.
Rack
If you are not using a Hitachi Universal Rack, make sure the electrical specifications of your rack meet the power requirements of the storage system as specified in the Hardware Guide for VSP One Block 20 Series.
Tools, equipment, and personnel
The following items are required for storage system installation:
  • Screwdriver with PZ-2 head. A Phillips screwdriver is also acceptable.
  • 2 units of available rack space with power supply
  • 2 people to lift and rack the storage system
  • Client PC

    For hardware, software, and web browser requirements for the client PC, see Requirements for the client PC.