- Install M5 caged nuts in the rear of the rack in the top and bottom square holes of rack positions U27 and U28 on both the left and right side of the rack.
- Slide the first switch into place in U27, taking care to align the rear mounting brackets on the switch with the mounting rails attached to the front of the rack.
- Secure the switch to the rack using four M5 screws.
Note: Although the graphic below shows the switch backwards, the principal is the same, and the general procedure should be followed.
1 Align the two rear rack-mount guides with slider rails installed in the rack. 2 Slide the rack-mount guides onto the slider rails until the front rack-mount brackets come in contact with the front rack-mount rails. 3 Mount switch using four M5 screws with plastic washers per switch. - Repeat steps 2 and 3 for the second switch. Install the second switch in rack position U28.
- Use two M5 screws with plastic washers to install two 1U perforated blanking panels in the front of rack units 27 and 28.
Important: Due to the height of the screws holding the rail kit to the rack, the panels do not sit flat on the vertical EIA rails of the rack. Do not overtighten the screws to compensate.