Locate the following items in the switch container:

  • Cisco N3K or N9K switch
  • 2 front rack-mount brackets
  • 2 rear rack-mount brackets
  • 2 slider rails
  • 12 M4 x 0.7 x 8-mm Phillips countersunk screws

Supply the following items (per switch):

  • Eight 10-32 or 12-24
  • Grounding cable
  • (Optional) Level tool or tape measure
  1. Set the required items aside in an easy-to-reach location.
  2. Leave the unused items in the switch container, and set the container aside.
    The rest of the items included in the switch container are not necessary for installation. You don't need the original power cords for the switches.