- Line up and slide the Brocade 6510 switch into the rails that are installed in the rack.
Push the switch all the way into the rack.
- Secure the port side of the switch using a screw in the middle square hole on both sides of rack unit U25.
- Repeat steps 1 and 2 for the other switch at rack unit U26.
- Install two vented panels in the front of the rack at rack units U25 and U26 using M5 screws.
The panels do not sit flush to the front of the rack since they are set on top of the screws for the mounting rail kit. Do not over-tighten the screws holding the perforated blanking panels.